We have had so much happen over the last three days. This is going to be lengthy!
Diebold has been working on moving the ATM into its location and communicating.
(We won't be putting the cash in until we open.)
My test transaction.
Front doors were installed.
The fence to hide the mechanical equipement went up.
My office was a busy place.
Cabinets for the coffee bar arrived and started to go into place.
Close up.
AT&T was on boaring under the road.
Essexville was installing the central air.
Data and security wires were being terminated.
Loan office and New Account office had the carpeting installed.
Meeting room floor was installed.
Sign foundation was poured.
Closet shelves went in.
Outside is getting its finishing touches.
The lobby and drive thru were getting the floor installed.